Important Information and Limitations

Beta. Both SOV sections are marked Beta in the menu. Layout and behavior may still change.

Editing rules

  • Nothing is saved until you click Save Changes. Leaving the page or clicking Reset All Changes drops unsaved edits.

  • Unit and Units cost can be set only on new rows. After a row is saved, they cannot be changed.

  • Pay item No. and Owner pay item cannot be changed once the row is in a pay application.

  • Previous changes and New changes come from change orders. You cannot type in them directly.

  • Contract estimated cannot be set lower than what has already been billed on that row. Deleting rows and groups

  • A row linked to a change order cannot be deleted. The tooltip links to that change order.

  • A row that is in a pay application and has a JTD - previous estimate value cannot be deleted.

  • The Default group cannot be renamed or deleted.

  • Deleting a group cannot be undone, but its rows are kept. Pay applications

  • Only one pending pay app is allowed per contract or vendor. If one is pending, you see Cannot Generate New Pay App. Certify or uncertify the existing pay app first. Click View Pending pay app to open it.

  • Generate pay app stays disabled while there are unsaved changes or cell errors.

  • A mismatch between the Contract estimated total and the contract value shows a warning on the TOTAL row, but it does not block generating a pay app.

  • Another pay app with the same Period to date for the same vendor shows a warning.

  • The table is disabled while a pay app is being certified or uncertified.

  • Pay app number start is locked once any pay app is certified. Vouchers (Subcontract SOV only)

  • The Voucher step is available only when the pay app status is not Draft and the vendor has a vendor number.

  • Voucher generation needs the project to be connected to accounting. Otherwise you see "Project is not connected to the Accounting".

  • The voucher invoice number always matches the pay app number and cannot be changed. Dependencies

  • Original Contract and the total check use the signed prime contract (Revenue SOV) or the vendor's signed master contract (Subcontract SOV).

  • All Cost Bill To Date comes from the All Costs page.

  • Approved change orders feed Previous changes and New changes. Unapproved ones appear on the Pending Change Orders tab.

  • Money is rounded to the project's revenue rounding setting.